기후정보를 이용한 초고층 건축 골조공사의 확률적 공기산정 모델 : Probabilistic Model to Forecast the Duration of Structural Work in High-rise Building Construction Considering Weather Elements
Cited 0 time in
Web of Science
Cited 0 time in Scopus
- Authors
- Issue Date
- 2007
- Citation
- 대한건설학회논문집 구조계, 23(6), pp.123-132
- Keywords
- 초고층 건축 공사 ; 골조공사 ; 기후 영향 요인 ; 시뮬레이션 ; 확률적 공기산정 ; High-rise Building Construction ; Structural Work ; Weather Influence ; Simulation ; Probabilistic Duration Forecasting
- Abstract
- The duration of a construction project is not only a key element for taking a new order, but also a strict yardstick to
determine a certain project successful or not. While construction project is full of uncertainty and contains many risk factors,
however, the current schedule planning work relies on traditional deterministic scheduling methods. Among the all construction
processes, the structural work is basically an outdoor work and most of the activities are proceeded out-air, that no matter how
the schedule plan has been established accurately, an actual project is mostly affected by the weather condition, beyond anyones
control. Thus, the weather condition and the work cycle time for a unit section among many risks, have been chosen as main
two factors to calculate the duration of structural work. The aim of this research is to present a probabilistic model to forecast
the duration of structural work in high-rise building construction considering weather elements.